TV cook Delia Smith has come out against a proposed £1.2bn data centre at Keswick, on the edge of Norwich in Norfolk, England. She says it would do nothing for the local community and that "it's going to be bad". Campaigners fear noise pollution and harm to the nearby Marston Marsh reserve. Developer Norwich Apex says its ecological impact assessment found no effect on the reserve is expected. The row comes as a separate solar farm and data centre plan in West Norfolk is heading to a Westminster debate on data centres in rural areas.

Why Is Delia Smith Opposing the £1.2bn Norwich Data Centre Plan?

The Short Answer

Television cook and author Delia Smith opposes a proposed £1.2bn data centre at Keswick, on the edge of Norwich in the English county of Norfolk. She says the project would do nothing for the local community, and she told the BBC that "it's going to be bad" for the county.

She is backing local campaigners who fear the site would bring noise pollution and harm the nearby Marston Marsh reserve. The developer, Norwich Apex, rejects the environmental concern. It says an ecological impact assessment concluded that no effect on the reserve is expected.

What Happened

Smith shared her view in a BBC video report on the Keswick proposal. Many people outside the UK know her as one of Britain's best-known cookery writers. In Norfolk she is also a big name in football: she is honorary life president and former majority shareholder of Norwich City FC.

She isn't the only well-known critic. TV presenter Jake Humphrey also spoke against the plan and said the countryside was "not for sale".

Key Facts

  • Project: A proposed data centre at Keswick, on the edge of Norwich
  • Reported value: £1.2bn
  • Developer: Norwich Apex
  • Campaigners' concerns: Noise pollution and harm to Marston Marsh
  • Developer's position: Its ecological impact assessment found no expected effect on the reserve
  • High-profile opponents: Delia Smith and Jake Humphrey

The sources do not give a decision date for the Keswick plan or say which planning stage it has reached. No timeline should be treated as confirmed until officials publish one.

Part of a Wider Norfolk Debate

Keswick is not the only data centre plan facing opposition in Norfolk. In West Norfolk, a separate private project called Longmarsh would combine a large solar farm with a co-located data centre around Tilney St Lawrence.

According to a column by South West Norfolk MP Terry Jermy in Lynn News:

  • Longmarsh would cover 4,695 acres, a large share of it grade two or better agricultural land.
  • Jermy raised the scheme with the Prime Minister at Prime Minister's Questions (PMQs).
  • As part of the pre-application consultation, he sent the developer's London-based CEO a 12-page letter of formal objection.
  • He has secured a Westminster Hall debate on data centres in rural areas, where he plans to put his concerns to government ministers.

Jermy says he supports renewable energy. He argues that it should not come at the cost of food security and that falling profits for farmers are pushing landowners to look at other uses for their land. He also notes that final details of Longmarsh have not yet been released and that the project has not yet gone to government review.

Why This Matters Beyond Norfolk

Across the UK and in other countries, demand for data centres is pushing developers into rural and semi-rural areas. The two Norfolk disputes show the main points of conflict:

  • Environment: Effects on protected or valued sites such as Marston Marsh
  • Community benefit: Whether local people gain anything from large projects
  • Land use: Whether farmland should be used for energy and digital infrastructure

For readers outside Britain, Norfolk is a largely rural county in the east of England. Norwich is its main city.

What Happens Next

  • Keswick: Opponents and Norwich Apex disagree on the environmental impact. The sources give no confirmed decision date.
  • Longmarsh: The developers have not yet released final details, and the plan has not reached government review.
  • Parliament: The Westminster Hall debate on rural data centres is due to take place the week after Jermy's column, published 28 November 2026. That puts it in early December.

What ministers say in that debate could show how the UK government plans to balance new data infrastructure against local opposition.